Putrajaya Mosque Erection of Steel Trusses

Infrastructure

In the construction of the Putrajaya Mosque, Tuck Sin Engineering and Construction Sdn Bhd (steel fabricator specialist) had worked together with Trans Elite for the steel erection works.
In order to speed up the erection time and to avoid the installation of a temporary tower, Trans Elite’s Engineering Department had come up with the rigging studies and recommended using the Demag AC1600 (500 tonnes) Truck Crane complete with luffing jib with superlift counterweight to lift and erect the steel girder at the working radius of approximately 63 meters.
Previous
Next
Previous
Next
Photo showing the main girder used to support the dome of the mosque which was erected using one (1) unit 500 tonnes All Terrain Crane (Demag AC1600) complete with lufffing jib.
There were 20 section numbers of steel girder that needed to be erected with the heaviest piece weighing at 24mt. The job was succesfully completed ahead of planned schedule.
You can`t add more product in compare

KA1200 KATO 120T

ZR280C ZOOMLION DRILLING RIG - VAV 6129

60T Rough Terrain Crane - RTT60 - 0261

60T Rough Terrain Crane - RTT60 - 0250

60T Rough Terrain Crane - RTT60 - 0259

60T Rough Terrain Crane - RTT60 - 0258

60T Rough Terrain Crane - RTT60 - 0257

ZR280C ZOOMLION DRILLING RIG - WC 6992 B

ZR280C ZOOMLION DRILLING RIG - VAV 9216

AC100 DEMAG 100T

ZR280C ZOOMLION DRILLING RIG - BPS 8639

ZMC85 ZOOMLION 85T - VE8860

ZMC85 ZOOMLION 85T

ZMC60 ZOOMLION 60T

ZOOMLION 85T

AC200-1 DEMAG 200T

55T Rough Terrain Crane