Our company was engaged to supply cranes ranging from 25 Ton to 300 Ton Hydraulic Truck Cranes, equipment such as air compressors, welding sets, generators, forklifts and a team of experienced manpower to supervise and carry out the structural erection and electrical installation for two (2) units of Super Post-Panamax Selferecting Gantry Cranes at the West Port of Port Klang.
Our scope of work also include the erection of boogies, sea side and land side portals, “A” frames, tie beam, lower & upper diagonals, horizontal internal and external diagonals, fixed girders, trolley, boom, luffing, electrical, hoisting platform and etc.