We have secured a heavy lifting job to supply one (1) unit Prime Mover complete with Multi-axle trailer, two (2) units 300 Tons Truck Crane to off load two (2) units of Tunnel Boring Machine from the vessel at West Port and provide transportation of the Tunnel Boring Machines to the jobsite at Jalan Pantai Dalam & Brickfields. Upon arrival at the jobsite, these two TBM is lifted by two (2) units 300 Tons Truck Crane from the Multi-axle trailers and lowering into the pit hole which our job include the supervision and final alignment on to the track. Rigging studies with supporting drawings are prepared and issued by us in order to analyze and plan the lifting procedures before commencing the project.