The job had to be well planned and organized mainly on the logistics due to a very limited time frame allowed to work on the public road (only 6 hrs. per operation). The job was successful executed in 8 straight nights along Jalan Tun Razak highway with the total road closure assisted by the traffic police.
Two (2) units of 160 tonne Truck Cranes rigging on a bridge to lift and erect 2 pieces of a Mid Span girder by bolt connection. (Total bolt joint – 930 nos).
The erection of the steel box girder for Package 1, Putrajaya Highway was carried out by Trans Elite Equipment Rental Sdn Bhd in September 2007.