SCOPE OF WORKS :
- Two (2) units – 350 tonnes Crawler Crane (Manitowoc 4600 S5).
- One (1) unit – 70ft x 250ft Heavy Duty Barge Singa Besar 2502 with 2 nos. double drum (10 tonnes) winch and 4 nos. 5 tonnes Anchor.
- One (1) unit – 1600 HP Tug Boat.
- One (1) unit – 1600 HP Anchor Tug.
Two (2) units 350 tonnes Crawler Crane (Manitowoc 4600 S5) rolling into the barge Singa Besar 2502 (70’ x 250’) at Port Klang.
Penang Bridge Widening Project for Marine Launching Works had been awarded to Trans Elite in February 2008. With immediate arrangements from our side, after we conducted proper rigging studies, presented proposal to our client and subsequently, we supply our manpower and equipments as listed above to execute this project.
Barge Singa Besar 2502 (70’ x 250’) loaded with (2) units 350 tonnes Crawler Crane berthing at Penang private jetty.
Our crew consists of Barge Master, lifting supervisor, winch operators, crane operators and riggers. Our scope of works was to provide two (2) units 350 tonnes Crawler Crane working on the barge for launching of 544 nos. x 40 meter long U-Beam (140 mt) and I-Beam (90mt) on to the newly cast crosshead along side of the existing Penang Bridge. The barge was required to position within 2 meters away from the existing bridge. On the other hand, we were requested to use 4 points 5 tonnes anchor to slowly position the barge, in order to moor the barge to the final allocated safe position without touching the pile cap of the bridge. Once the barge is in the correct position, we then lower down 2 nos. of spar on to the seabed to hold and stabilise the barge while launching of the beams.