KL Monorial Train
On 19 April 2002, the first locally made KL Monorial train was successfully lifted onto the track at the Jalan Maharajalela Station by our company
On 19 April 2002, the first locally made KL Monorial train was successfully lifted onto the track at the Jalan Maharajalela Station by our company
We have secured a heavy lifting job to supply one (1) unit Prime Mover complete with Multi-axle trailer, two (2) units 300 Tons Truck Crane
In the LRT Project, we supplied one unit of 300 Ton Liebherr LT 1300 Hydraulic Truck Crane with technical drawings and our manpower to supervise
Lifting & lowering TBM components with heaviest item (TBM Front Shield) weighing 159T at Cochrane MRT Station using 300Ton Ringer Craneassisted by 1 unit 150Ton
Lifting TBM components with heaviest item (TBM Front Shield) weighing 137T at Semantan using 300Ton Ringer Crane & assisting by 1 unit 160Ton Crawler Crane
Erection of overhead Gantry Crane using 160Ton Crawler Crane / 200Ton Crawler Crane and 160ton Truck Crane.
Our company Trans Elite also provided services for assessing crane counter weight load test from 5mt to 400mt including load test on spreader / lifting