SCOPE OF WORKS : Rigging studies with Autocad drawings. Supply
Zoomlion QUY650 (650 ton) crawler crane as main crane to
Lifting of Concrete U-Beam with 29 meter length & weight
In March 2018, the QUY650 Zoomlion 650-ton crawler crane operated
Ship builders, NGV was responsible to fabricate the Patrol Boat,
Lifting of a 86 Tonnes Helideck for the Maari Project
Petrochemical / Oleo Chemicals Plant Plant Extension of KLK Olemas
We have been appointed by Leighton Contractors (M) Sdn Bhd
In the construction of the Putrajaya Mosque, Tuck Sin Engineering
SCOPE OF WORKS : Two (2) units – 350 tonnes
A steel box girder being lifted by one (1) 500
Lifting of Steel Girder with 50.6 meter length & weight
Our professional services have been called upon to take part
On 19 April 2002, the first locally made KL Monorial
We have secured a heavy lifting job to supply one
In the LRT Project, we supplied one unit of 300
Lifting & lowering TBM components with heaviest item (TBM Front
Lifting TBM components with heaviest item (TBM Front Shield) weighing
Erection of overhead Gantry Crane using 160Ton Crawler Crane /
Shipment of Piling machines, Diesel Piling Hammers and parts for
Loading of Tadano Rough Terrain Crane to the vessel for
Trading of Construction Equipment Export for sales to Sudan for
In July 2009, we again being awarded by IMPSA (M)
Load out of the Suction Anchor (148mt) and Gem Manifold
Our company was engaged to supply cranes ranging from 25
In 2002, our company was engaged to supply experienced manpower,
We provide manpower (rigging supervisor, riggers, crane operators), two (2)
Lifting of 1 unit Deaerator Vessel 5364mm diameter x 23m
The 100 tonnes cutter ladder of the dredging barge was
Lifting of Cold Box and Vessel for Air Product Sdn
In October 2007, we undertook an urgent & critical Heavy
We were engaged to carry out the erection supervision and
Our company was awarded the Contract to Supply Crawler Cranes
We were engaged to carry out a very complicated tandem
We have secured a heavy lifting project to lift and
Petrochemical / Oleo Chemicals Plant SCOPE OF WORKS: Rigging studies
Replacement Of E1801-Reactor (125mt) At Petronas Refinery Kedah Petrochemical /
Petronas Fertilizer Plant at PFK, Guran Petrochemical / Oleo Chemicals
PML-Plant Rejuvenation at Labuan Petrochemical / Oleo Chemicals Plant We
Our company Trans Elite also provided services for assessing crane
Petrochemical / Oleo Chemicals Plant Precision planning is crucial for